Construction Update on 481 Hammond St.

Construction is moving along on the addition at Chestnut Hill Center, 481 Hammond Street.  A lot of the exterior work is done. Most of the landscaping will be done this month on the Hammond Street and Suffolk sides.  Plantings and fences will be installed in the area between us and the church over the next month. Drywall is almost complete inside and many of the walls are painted.  Trim work has started.  Kitchen equipment will be brought in at the end of October.  The work on the elevator will start soon.  Target date for finishing the addition is December.  Then we start on the renovations to the existing house.  Target date for that is April to May, 2013. If you have questions of concerns, please contact Joseph G. Billmeier ( jgbillmeier@gmail.com)